You’re Invited to a Public Meeting On the Widening of University Avenue from Avenida de Mesilla to South Main Street

Monday, November 18, 2024 • 5:30-7 p.m.

Posted

Monday, November 18, 2024 • 5:30-7 p.m.
Zia Middle School Cafeteria
1300 New Mexico State Road 101, Las Cruces, NM 88005

Purpose of Project
The project includes widening of 1.419 miles of University Avenue/New Mexico State Road 101 from Avenida de Mesilla to South Main Street. It also includes new curb and gutter, sidewalks, a multi-use path, ADA ramps, drainage structures, storm drain, new signage and roadway striping, new lighting and railroad crossings.
Construction is scheduled to begin on Tuesday, November 26, 2024 and last through fall 2026.

Purpose of Meeting
At this meeting, the construction team will review anticipated construction phases, expected traffic impacts and detours, and the timeline for project construction. Team members will also answer questions and received comments.
To request Americans with Disabilities Act (ADA) related accommodations, please contact Ami Evans at 575-640-5981 or ami.evans@dot.nm.gov.